Projects by Defence Capability Investment Area
Support and Monitoring Systems
3 projects were found under "Support and Monitoring Systems". (Select another Defence Capability Investment Area).
| Project | Funding Ranges | Definition Approval | Implementation Approval | Initial Delivery | Final Delivery | Project Sponsor |
|---|---|---|---|---|---|---|
| Enhanced Satellite Communications Project - Polar | Greater than $5 billion | 2029/2030 | 2029/2030 | Beyond 2035 | Beyond 2035 | Royal Canadian Air Force |
| Surveillance of Space 2 | $250 million to $499 million | In Progress | 2025/2026 | 2026/2027 | 2031/2032 | Royal Canadian Air Force |
| Tactical Narrowband Satellite Communications-Geosynchronous | $500 million to $1 billion | Completed | In Progress | 2024/2025 | 2025/2026 | Royal Canadian Air Force |